Extra work items push back Destin 98 finish date

www.thedestinlog.com

Construction on the U.S. Highway 98 Destin Improvement Project has pushed its finish date back three months, at least, because of additional work items, according to The Destin Log.

The project's construction team added 96 contract days to the original contract to install another turn lane into the Emerald Grande parking lot and a blinking sign on the Marler Bridge to warn oncoming drivers of signals ahead and stopped traffic.

The total additional costs for the work will be $150,000.